Application for Net Metering
Net metering is a program with a billing mechanism that allows consumers who generate their own electricity (typically via solar photovoltaic (PV) systems) to sell excess electricity back to the grid. It’s a key part of the country’s renewable energy strategy under the Renewable Energy Act of 2008 (Republic Act No. 9513).

Application

Evaluation

Inspection

Completion

Energization
Application
Requirements | Remarks |
Letter of Intent | The letter must be addressed to the General Manager |
Application Form | Applicants can request the form in NORECO I Main Office. |
Identification Documents | Valid ID and/or NORECO I membership ID |
Certificate of Good Standing | This will be issued by the Finance Services Department if the applicant (existing) is found to have settle all his obligations to NORECO I |
Membership (for new customers only) | A certificate or ID is issued to all who have succesfully complied with all the requirements for membership |
Electrical Plan with RE facility interconnection set-up duly signed and sealed by a Professional Electrical Engineer (PEE) | c/o Applicant |
Spot Diagram/Typical PV System Layout | c/o Applicant |
Electrical Permit (for new connection applicant) | c/o Applicant |
Product specification of inverter and solar panel | c/o Applicant |
Location Map of the Facility | c/o Applicant |
Evaluation and Inspection
Requirements | Remarks |
Certificate of conduct of Distribution Impact Study (DIS) | A DIS shall be conducted by NORECO I to ensure the reliability and safety of the interconnection of the Renewable Energy (RE) facility system and the Distribution System. A Certificate shall be issued if such interconnection is acceptable based on applicable standards. No DIS fee shall be collected. |
Proof of payment of applicable fees to NORECO I | c/o Applicant |
Certificate of Final Inspection and Completion | This certificate is issued by the Technical Services Department (TSD) as proof of Final Inspection and Completion, and that the facility has complied with all requirements in accordance to applicable standards |
Copy of accomplished form with Data During Testing and Commissioning | c/o Applicant |
Other data as may be required by the handling officer | c/o Applicant |
Energization and Compliance to Regulatory Requirements
Requirements | Remarks |
Duly accomplished Energy Regulatory Commission (ERC) Forms: QE-COC Application Form No. 1; and QE-COC Application Form No. 1.1 |
Applicant and NORECO I |
Duly notarized Net Metering Agreements (6 copies) | Applicant and NORECO I |
Php 1,500.00 COC Fee | Applicant |
Having all the requirements complied, the interconnection shall now proceed with its energization | NORECO I |